Selected special works

Nine projects, from 16th-century frescos to eco pools.

Project 01

Royal Veterinary College, Accreditation Hoarding

This project comprised the erection of secure timber hoardings to obscure the view and limit access to 3 buildings, namely: OBS Barn, CIC & Structure & Motion building on the main RVC campus.

These works were awarded following on from the very successful project we completed to construct a Live Animal Handling Facility at Boltons Park Farm next to the main campus.

Client
The Royal Veterinary College
Contract Duration
4 weeks
Contract Value
£69,000
CA
The Royal Veterinary College
KPI Score
59/60
Royal Veterinary College, Accreditation Hoarding
Project 02

Cypress Gate, Stanmore

Adaptation and rebuild of a house to meet the needs of a disabled person.

Client
Private
Architect
ARA Architects
Contract Duration
22 weeks
Contract Value
£425,000
KPI Score
58/60
Cypress Gate, Stanmore
Project 03

Gascoyne Estate, Hatfield

Project No. 1 The refurbishment works in 2 No separate buildings contained within the wider Hatfield Park Estate; ‘The Old Palace’ and ‘The Riding School’. Project No. 2 The refurbishment / remodelling works of the existing WCs contained within the Estate Office of the wider Hatfield Park Estate.

Client
Gascoyne Estate
Quantity Surveyor
Press & Starkey
Contract Duration
18 weeks
Contract Value
£285,000 combined
KPI Score
57/60
Gascoyne Estate, Hatfiel
Project 04

The Wellcome Trust

This is one of numerous successful refurbishment properties we have undertaken for The Wellcome Trust

Client
The Wellcome Trust
Architect
Savills UK
Contract Duration
20 weeks
Contract Value
£480,875
KPI Score
60/60
The Wellcome Trust
Project 05

Black Swan House, Ware

Complete refurbishment ofa 16th Century former coaching inn, into modern offices whilst maintaining as much of the original fabric of the building as possible.

During the works, highly significant early 17th century painted plaster frescos were uncovered on the main chimney stack. The stack had a major crack in the brickwork which had to be carefully repaired without causing any damage to the mural.

Client
Green Energy UK
Architect & Contract Administrator
Wastell & Porter (proposed by NC)
Interior Designer
Newland Interiors
Contract Duration
21 weeks
Contract Value
£320,000.00
KPI Score
58/60

This project was a winner of the 2012 HAA Architecture Awards in the Conservation and Restoration Category.

We worked with our sister company, Newland Interiors, to carry out the final fixtures and fittings which included purpose made work desks.

Black Swan House, Ware View larger
Black Swan House, Ware
Project 06

Private House, Hertfordshire

Bespoke single storey extension to provide a new kitchen, utility, dining area and garage. Cantilevered floor to carry external patio area, sips panels to form external walls with Oak cladding and copper roof. Carried out repairs to existing single glazed two-storey cube abutting Grade II Queen Anne House.

Client
Confidential
Contract Administrator
Projekt Solutions
Contract Duration
28 weeks
Contract Value
£525,000
KPI Score
53/60
Roxford House, Newland Construction, building in Hertfordshire and surrounding areas View larger
Project 07

Childs Hill School, Cricklewood

Formation of new masonry amphitheatre within existing playground. Project received commendation at the Brick Awards

Client
London Borough of Barnet
Architect
Tim Foster associates
Contract Duration
6 weeks
Contract Value
£65,000
KPI Score
59/60
Reference from Childs Hill School, Cricklewood →
Childs Hill, Newland Construction, building in Hertfordshire and surrounding areas View larger
Project 08

Private House, Hertfordshire

External swimming pool and pergola with associated hard landscaping

Client
Private Clients
Contract Duration
12 weeks
Landscape Designer
Julie Wyse
Contract Value
withheld
KPI Score
59/60
Pergola, Newland Construction, building in Hertfordshire and surrounding areas View larger
Project 09

Eco Swimming Pool

Eco swimming pool with associated hard landscaping

Client
withheld
Contract Duration
8 weeks
Contract Value
withheld
KPI Score
58/60
Childs Hill, Newland Construction, building in Hertfordshire and surrounding areas View larger

Building for generations.

Independently verified memberships and standards that stand behind every project we deliver.

NHBC
Constructionline
CHAS
CITB
Let’s build together

Start your project.

01707 659222

Head Office Newland Construction Limited
St Vincents Way, Barnet Road,
Potters Bar, Hertfordshire,
EN6 2RW

Call us today →