As developers and contractors since the 1920s we have a vast experience of New Build works. Unfortunately the cost of a house is not what it was then and the options available to our clients have grown considerably! New clients have the choice of traditional build techniques right through to advanced off-site fabrication and renewable energy techniques.
We have always taken great pride in the quality of our workmanship but our housing clients have the further reassurance that our homes are covered by a ten year NHBC Warranty.
As well as housing we also have a history of new build works for Schools, Hospitals and Commercial Clients.
This project which comprised the demolition of an existing building and the new build construction of a new Live Animal Handling Facility and Teaching Facility by way of structural steel frame, cavity brickwork, Kingspan and timber cladding and cementitious roof with associated mechanical, electrical, drainage services, site and finishing works.
The building comprised of classrooms/mezzanine overlooking barn area, Student common room, meeting rooms, changing rooms, boot cleaning room, storerooms, laundry room, dirty/wet Labs, plant room, barn area for live animals and toilets & showers
- Client: The Royal Veterinary College
- Contract Period: 48 weeks
- Contract Value: £2,900,000
- CA: ACD Projects
- KPI Score: 60/60
Erection of three storey block of three flats and single dwelling to rear of site with associated ground works and landscaping.
- Client : Private
- Architect : Lawrence Vacher LLP Chartered Surveyors.
- Contract Duration : 38 weeks
- Contract Value: £649,850.00
- KPI Score: 58/60
Demolition of existing bungalow and erection of 12 no luxury apartments in two blocks, constructed in a mixture of brick facings and cedar cladding
- Client : St. Cross Developments Ltd
- Architect : Sewell & Hawkins
- Quantity Surveyor : Payne Cole Partnership
- Contract Duration : 43 weeks
- Contract Value: £1.4 million
- KPI Score: 58/60
Demolition of existing single storey building and erection of new church with mezzanine floor
- Client: Elim Trust
- Contract Administrator: Cawley Billing Partnership
- Contract Duration: 52 weeks
- Contract Value: £540,000.00
- KPI Score: 53/60
Design and build of a new school hall, classroom, toilets and changing rooms.
- Client: The Governors of Cowper School
- Contract Administrator: Wilby & Burnett
- Contract Duration: 22 weeks
- Contract Value: £439,000.00
- KPI Score: 58/60
Construction of a new timber structure classroom, consisting of teaching areas, toilet, disabled toilet & kitchen. we also installed a greenhouse and garden shed, along with landscaping and artificial grass.
The Classroom was awarded “Best Educational Building” by the Building Excellence Awards 2017.
- Client : Governors of Ardeley School
- Architect : Hox Design
- Contract Duration : 25 weeks
- Contract Value: £304,195.00
- KPI Score: 58/60
Demolition of old existing bungalow, removal of trees and construction of a new chalet bungalow, new drive and access and new shed.
- Client : Chamberlain Holdings Plc
- Architect : Wastell & Porter
- Contract Duration : 24 weeks
- Contract Value: £257,552
- KPI Score: 60/60
Demolition of the Existing prefabricated building at Hackney, excavation of new footings and the construction of a new TA Centre.
- Client : RFCA Greater London
- Architect : Ednie Stroud
- Contract Duration : 26 weeks
- Contract Value: £385,095.00
- KPI Score: 59/60